Woodbury
Middle Years Building
Originally Constructed: 1918
Original Architect: Franz Warner
Wings added: 1931 (now demolished)
WIngs Architect: Howell and Thomas
Gym addition: 1958 (now demolished)
Pool addition: 1969 (now demolished)
Building History:
Initially constructed for use as the senior high school, it became a junior high school after the current high school was constructed.
In 1985, the building was closed and junior high occupancy was concentrated at the Byron building. In 1987, it became known as Woodbury Elementary, serving grades 5 and 6. It was closed at the end of 2022-2023 school year, and construction work started in 2025 with abatement and selective demolition.
Costs for renovation of Woodbury School for use as the Middle Years Building are funded by a portion of the bond levy approved by voters on the November 2023 ballot (Issue 13).
2023 Enrollment:* 642 students (grades 5-6)
(321 per grade average)
2019 Enrollment: 763 students
(382 per grade average)
2015 Enrollment: 838 students
(419 per grade average)
2023 Bldg. Capacity: 981 students
Grades served: When renovations and additions are complete in 2027, the building will serve grades 6-8.
*Woodbury was closed after the 2023-24 school year, with 5th grade students integrated into existing elementaries, and 6th grade students relocated to the Middle School (Byron) campus swing space. Current 2025-26 enrollment for grades 6-8 is 930 students, an average of 310 students per grade.
Site amenities:
The front lawn of the building has historically been open for formal and informal athletic use. A track and field oval is shared with the Onaway campus.
These features remain in the new site plan, with the oval length shrinking slightly while retaining a full-sized play field.
The District maintains a page with information about the Woodbury renovations here.
Renovation Architect: GPD Group / RPMI**
Design Consultant: Bialosky + Partners***
Architectural/engineering services and reimbursable expenses are performed under a $12 million blanket contract for facilities master plan work.
** GPD holds the prime contract and is responsible for project management, and provided work for exteriors, demo, engineering, furniture, graphics, and approvals. Additionally they lead engagement and management subconsultants for the pool, LEED certification, testing, etc. RPMI is responsible for the interiors and interior architecture, including associated documentation and construction administration.
***Bialosky was engaged directly on by the School District to assist with Woodbury exterior design on 5.13.2025, after the project appeared at the 4.8.2025 Planning/Zoning meeting. At that meeting, CPC-BZA members had expressed concern regarding the design progress and quality.
Construction Manager: Gilbane Building Co.
Building Area: 66,839 sq. ft. existing to remain
119,423 sq. ft. additions
186,262 sq. ft. total
Site Area: 22 acres (shared w/ Onaway)
Project Construction Budget:
Initial OFCC budget: $61,602,983
Design Development: $69,783,385
(includes $15.56m for locally funded initiatives (LFIs), the auditorium and natatorium with no State cost share)
Unit Costs: $375 per sq. ft. total project
Renovation portion $209 per sq. ft.
New const. portion $435 per sq. ft.
Project Schedule:
Design Start September, 2024
Bldg. Demo Start May 19, 2024
Planning Approval November 5, 2025
Construction Start October 5, 2025
Scheduled Finish July 30, 2027
School Start
Scheduled August 2027
Shared facilities: The building design includes addition of a new gymnasium. It also includes Locally Funded Additions of an auditorium ($5.1m) and natatorium ($10.5m), funded by the district without a corresponding cost share contribution from the State of Ohio.
The building is designed to accommodate community use of these spaces, with the ability to secure the educational portions of the building from access at times these areas are open to the public.