LUDLOW PRE-K

Ludlow Early Learning Center

Originally Constructed: 1922
Original Architect:         Charles S. Schneider​

Building History:

Initially occupied as a Shaker Elementary, this neighborhood school played a significant role in the initial integration of Shaker Heights and the Shaker Schools.

Ludlow School was one of four schools closed by the Board of Education in 1987. It was later leased for use by the Positive Education Program (PEP), with that use continuing until Spring 2023.

Costs for renovation of Ludlow School for use as the Ludlow Early Learning Center were funded by a portion of the bond levy approved by voters on the November 2023 ballot (Issue 13). This ballot issue also included a 3.0 mill operating levy for this Pre-K, yielding approximately $2.8 million annually.

2025 Enrollment:          141 preschool students

Building Capacity:    +/-200 students

Funding: The Ludlow renovations were funded by the 2023 Issue 13 levy. This preschool facility is a Shaker Schools initiative without co-funding from the State of Ohio.

Playground: The 2025 renovations included construction of a new playground, with equipment added that can serve community children of all ages in addition to the preschool-aged children.

The playground area is approx. 6,300 sq. feet

(5,575 sq. ft. playground, 725 sq. ft. paved play area).

 

Other Site amenities: The Ludlow property includes a play field with softball diamond and backstop and open field areas. The smaller dimensions of this field do not allow regulation play for older children, but are appropriate for T-ball and soccer events for younger players as well as general community use.

The District maintains a page with information about the Ludlow Preschool renovations here.

Renovation Architect:     GPD Group

Architectural services     $995,771

                                             (7.1% of const. budget)

Reimbursible expenses  $335,000

09.12.2023 GPD Group Contract Authorization

Construction Manager:  Gilbane Building Company

Site Area:                        3.60 acres total

Building Area:                 38,462 sq. ft. existing

                                             766 sq. ft. additions

                                        39,228 sq. ft. total

Project Construction Budget:             

Initially approved:          $14,025,000

At Construction Start    $14,780,969 

                                      (+5.39% above initial amt.)

Change Orders:            $  1,091,216

                                                  (+7.38% additions)

Current Cost:                 $15,872,185 

                                                   (+13.17% compared to initial budget)

Unit Cost :                     $405 per sq. ft.

Project Schedule:

   Design Start              October 2023

   Demo Start                October 21, 2024

   Planning Approval     December 3, 2024

   Construction Start     January 14, 2025

   Scheduled Finish      August 1, 2025

   Actual Finish             Work still in progress

   Completion Delay     6 months and counting                       

 School Start

   Initially Scheduled    August 21, 2025

   Actual                       September 15, 2025​​

Estimated tuition loss

due to delayed start:    $112,000*

*Details on lost tuition have been requested from Shaker Schools but not yet confirmed. It is our understanding that September 2025 tuition was not charged due to the inconvenience of the delayed start.

Estimate above assumes 70 students at full $1000/mo. full-rate tuition, and 70 students at $600/mo. IEP rate.

Shared facilities: The building includes a small gymnasium which has been designed to accommodate community use. The gym can be accessed directly from the new building entry and includes restroom access, so the space can be used without accessing the rest of the building. The building also includes a small auditorium with a stage.

Key Project Issues

Ludlow entrance: April 2024 design
An early design for the entrance of the Ludlow Pre-K, with an entry canopy resemblying an early Wright Brothers flyer suspended above the doors.

Initial entrance design presented to the Architectural Board of Review and Board of Education.

Project Documents

Facility assessment
Tree assessment
Design
Project schedule
Budget
Punch lists / incomplete work
Project Change Orders
Change Order #001   $     9,211.41 - Gilbane provided BRI
Change Order #005   $  14,266.00 - PR-004
Change Order #006   $    5,564.00 - PR-005 Floor Type Revisions & Lockers
Change Order #007   $    3,445.00 - Electrical Revisions
Change Order #008   $ -19,125.00 - Technology Equipment Revisions
Change Order #011   $    3,078.00 - RFI #063 - Existing Slab Structural Integrity Detail
Change Order #013   $    1,943.00 - RFI #071 RTU 1 & 2 Supply Air Duct Drops
Change Order #014   $   12,216.00 - PR 008/008.1
Change Order #015   $    2,516.00 - RFI #113 Existing Conditions at New Column
Change Order #016   $ -23,039.00 - Roofing VE Alternate
Change Order #017   $    1,999.00 - RFI #078 Existing Louver in Rms 212 & 215
Change Order #019   $  15,031.00 - RFI #046 Wall Tile
Change Order #021   $  16,864.00 - PR-07 Owner Allowance Reconciliation, Multiple RFIs, Misc. AHJ
Connect With Us
Build Shaker Better

is an independent, citizen-led website. It is not affiliated with the Shaker Heights City School District or the City of Shaker Heights.

Questions, submissions, and corrections are welcomed.